Integrated Planning and Delivery
PMP PMP · Process
What integrated planning means
The Process domain opens with one of the largest tasks in the July 2026 ECO: develop an integrated project management plan and plan delivery. "Integrated" is the key word. A project has many moving parts — scope, schedule, cost, quality, resources, communications, risk, procurement, stakeholders — and each has its own plan. The project management plan pulls them all together into one coherent whole, so that a decision in one area is checked against its effects everywhere else. A schedule change that ignores cost, or a scope decision that ignores risk, is not a plan; it is a guess. The exam tests whether you think in this integrated way, and situational questions constantly reward the option that considers the whole project before acting on one part of it.
The project management plan is not a single document written once and filed away. It is a set of subsidiary plans (scope, schedule, cost, quality, resource, communications, risk, procurement, stakeholder engagement) plus three baselines — scope, schedule, and cost — against which performance is measured. It is created during planning, approved by the sponsor and key stakeholders, and then updated through integrated change control whenever an approved change affects it. The exam expects you to know that the plan is a living document: a question describing a project manager who refuses to update the plan after an approved change is describing bad practice.
It starts with the charter
Before there is a plan, there is a project charter — the document that formally authorizes the project and gives the project manager the authority to apply resources to it. The charter is issued by the sponsor, not written by the project manager alone, and it records the project's purpose, measurable objectives, high-level requirements, key stakeholders, major risks, milestones, and budget. The exam tests the charter in two ways. First, the project manager's authority comes from the charter: without it, you have no mandate to spend money or direct resources. Second, the charter is the project's anchor: when scope arguments arise later, the charter (and the business case behind it) is the reference point for what the project is for.
Closely related is the business case, which justifies the project in financial and strategic terms — why this project, why now, what return is expected — and the benefits management plan, which describes how the project's benefits will be measured and realized after delivery. The exam sometimes asks who is responsible for the business case (the sponsor) and when it is revisited (throughout the project, as conditions change — a project whose business case no longer holds should be questioned, not blindly continued).
Baselines: the lines you measure against
A baseline is the approved version of a plan against which performance is compared. The scope baseline is the approved scope statement plus the work breakdown structure (WBS) and the WBS dictionary. The schedule baseline is the approved schedule, with its milestones and critical path. The cost baseline is the approved, time-phased budget — the spending plan over time, which is also the planned value (PV) curve used in earned value management. Together, the three baselines form the performance measurement baseline. The exam expects you to know that baselines change only through formal change control: a project manager who quietly moves a deadline or adds scope without approval is breaking the baseline, not managing the project.
This is also where the exam tests the difference between the cost baseline and the project budget. The budget equals the cost baseline plus the management reserve — money held by the sponsor for unforeseen work that is outside the current scope. The cost baseline itself includes the contingency reserve, money held for known risks that may occur. A question might ask who can authorize spending from the management reserve: the answer is the sponsor (or whoever controls it above the project manager), not the project manager. The contingency reserve, by contrast, is part of the baseline the project manager manages.
Directing and managing the work
Once the plan is approved, the project manager directs and manages the project work: leading the team, applying resources, producing deliverables, and managing the interfaces between the project's parts. This is the executing work, and the exam tests it through scenarios about what to do when reality diverges from the plan. The pattern is always the same: assess the variance, understand its cause and its impact across the whole project, and then choose a response — which may be a corrective action (bringing performance back in line with the plan), a preventive action (stopping a problem before it happens), a defect repair, or a change request. What you do not do is ignore the variance, or fix one part of the project while breaking another.
Work performance data is the raw material for all of this: the actual measurements of what has happened — work completed, costs incurred, defects found, schedule progress. Work performance information is that data analyzed and put into context: earned value figures, variance analysis, forecasts. Work performance reports are the formal documents that communicate the information to stakeholders. The exam sometimes tests the distinction between data, information, and reports, usually with a question about what a status meeting should be based on (information and reports, not raw data).
Planning delivery across predictive, agile, and hybrid approaches
The 2026 ECO is explicit that the exam covers predictive, agile, and hybrid approaches, with roughly 60% of questions reflecting agile, adaptive, or hybrid ways of working. Integrated planning looks different in each. In a predictive project, the plan is detailed up front: the full scope is defined, the schedule is built for the whole project, and changes go through formal control. In an agile project, planning is rolling and adaptive: the team plans in detail for the next iteration and keeps the longer-term plan at a higher level, refining it as learning accumulates. In a hybrid project, the two are combined — for example, a predictive plan for the overall timeline and budget with agile delivery of the software components.
The exam expects you to choose the approach that fits the situation, not to force every project into one method. High uncertainty, changing requirements, and a need for early feedback point toward agile. Stable requirements, regulatory constraints, and fixed scope point toward predictive. A question might describe a project with unclear requirements and a customer who wants to see working product early: the agile-first answer is to use iterative delivery with frequent reviews, not to spend months writing a detailed plan for requirements that will change. Conversely, a question describing a construction project with fixed regulatory requirements points toward predictive planning. The project manager's judgment about the approach is itself part of integrated planning.
Exam mindset for integrated planning
For integrated planning questions, the pattern is: think whole-project, not one-dimensional. Before acting on a variance or a request, assess its impact across scope, schedule, cost, quality, risk, and stakeholders. Use the plan and the baselines as your reference, and change them only through the proper process. Remember that the charter authorizes the project, the sponsor owns the business case and the management reserve, and the project manager owns the integrated plan. And when the situation involves uncertainty or changing requirements, lean toward the adaptive approach — the exam is agile-first, and the plan should fit the project, not the other way around.
Exam traps to watch for
- Changing a baseline informally. Baselines change only through integrated change control — a quiet deadline move or scope addition is a breach, not management.
- Confusing the contingency reserve (in the cost baseline, for known risks, managed by the project manager) with the management reserve (outside the baseline, for unforeseen work, controlled by the sponsor).
- Forgetting that the charter is issued by the sponsor and is the source of the project manager's authority — the project manager does not authorize their own project.
- Applying predictive planning to a high-uncertainty project. When requirements are unclear and feedback matters, rolling-wave and iterative planning beat a detailed up-front plan.
Practice questions
Test yourself on this guide. Answers are checked instantly, with a full explanation for each question.
Q1.A project manager discovers that a deliverable will be two weeks late. Before deciding what to do, what should the project manager do FIRST?
Explanation: The PMI reasoning chain is: assess before you act, and assess the whole project, not one dimension. A two-week delay to one deliverable may or may not affect the project's end date (it depends on whether the deliverable is on the critical path), and the right response depends on the full impact — on cost, on dependent work, on stakeholders. Only after that assessment can the project manager choose between options such as overtime, scope adjustment, or a change request. Option C is wrong because changing the baseline is a formal change-control decision, not something the project manager does unilaterally as a first step. Option A is wrong because overtime is a response chosen before the impact is understood, and it may be unnecessary or harmful. Option D is wrong because removing scope is a major decision that needs the same impact assessment first.
Exam objective: PMP ECO Task: Develop an integrated project management plan and plan delivery (Process)
Q2.A sponsor asks the project manager to approve spending $50,000 from the management reserve to cover an unexpected regulatory requirement. Who has the authority to approve this spending?
Explanation: The management reserve is held outside the cost baseline for unforeseen work that is outside the current scope, and it is controlled by the sponsor (or by management above the project manager), not by the project manager. Spending it requires the sponsor's approval — and the irony of the question is that the sponsor is asking the project manager to approve something only the sponsor can approve. Option D is wrong because the project manager manages the cost baseline (which includes the contingency reserve for known risks), not the management reserve. Option C is wrong because finance processes the payment but does not authorize the use of the reserve. Option B is wrong because the change control board approves changes to the baselines; releasing management reserve is a sponsor decision, though a baseline change may follow.
Exam objective: PMP ECO Task: Develop an integrated project management plan and plan delivery (Process)
Q3.A project manager is assigned to a new project but has not yet received a signed project charter. The sponsor asks the project manager to start hiring team members immediately. What should the project manager do?
Explanation: The project charter is the document that formally authorizes the project and gives the project manager the authority to apply resources. Without it, the project manager has no mandate to spend money or hire people. The right move is to explain this to the sponsor and work with them to get the charter issued promptly — the sponsor's verbal request is not a substitute for formal authorization. Option D is wrong because committing resources without authorization exposes the project manager and the organization if the project is later cancelled or changed. Option B is wrong because refusing all work is unnecessarily rigid — the project manager can prepare (for example, drafting plans) while the charter is being finalized, but should not commit resources. Option C is wrong because the charter is issued by the sponsor; the project manager cannot authorize their own project.
Exam objective: PMP ECO Task: Develop an integrated project management plan and plan delivery (Process)
Q4.A customer asks for a new feature that would add three weeks to the schedule and $40,000 to the cost. The project manager has confirmed the estimates. What should the project manager do NEXT?
Explanation: A change that affects scope, schedule, and cost must go through integrated change control: a formal change request is submitted, its impact is assessed, and it is approved (or rejected) by the authorized decision-maker before any work begins. This protects the baselines and ensures the customer understands the trade-off they are asking for. Option A is wrong because adding scope without approval is scope creep, even when the customer asked for it. Option B is wrong because refusing outright ignores the possibility that the feature is worth the cost — the change process exists to make that decision properly. Option C is wrong because hidden work is still scope creep, and it creates undocumented, untested, and unbudgeted deliverables.
Exam objective: PMP ECO Task: Develop an integrated project management plan and plan delivery (Process)
Q5.A software project has unclear requirements, a customer who wants to see working product early, and a market that changes quickly. Which delivery approach is MOST appropriate?
Explanation: Unclear requirements, a customer who wants early feedback, and a fast-changing market are the classic signals for an agile approach: short iterations, working product shown frequently, and a plan that adapts as the team and the customer learn. Option B is wrong because detailed up-front planning for requirements that will change wastes effort and produces a plan that is obsolete before it is used. Option A is wrong because uncertainty cannot be planned away — a longer planning phase just delays the learning that only comes from building and showing product. Option C is wrong because agile is not unplanned: it uses rolling-wave planning, a prioritized backlog, and iteration planning. 'No planning' is a caricature, not agility.
Exam objective: PMP ECO Task: Develop an integrated project management plan and plan delivery (Process)
Q6.Which of the following is part of the scope baseline?
Explanation: The scope baseline has three components: the approved project scope statement (what is included and excluded), the work breakdown structure (the deliverables decomposed into work packages), and the WBS dictionary (the detail for each work package). Option A is wrong because the charter and business case authorize and justify the project but are not part of the scope baseline. Option D is wrong because the schedule and cost baselines are separate baselines; together with the scope baseline they form the performance measurement baseline. Option C is wrong because the stakeholder register and communications plan are project documents and subsidiary plans, not baseline components.
Exam objective: PMP ECO Task: Develop an integrated project management plan and plan delivery (Process)
Q7.A project manager receives work performance data showing that 40% of the work is complete and $120,000 has been spent. To report status to the sponsor, what should the project manager do with this data?
Explanation: Raw work performance data (percent complete, money spent) is not yet useful information: the sponsor needs to know what it means — whether the project is ahead or behind schedule, over or under budget, and what is forecast. The project manager analyzes the data into work performance information (earned value metrics, variance analysis, forecasts) and communicates it through work performance reports. Option B is wrong because raw data without analysis leaves the sponsor to do the project manager's job. Option D is wrong because verbal updates are not a substitute for measured performance. Option C is wrong because reporting should follow the communications plan's schedule, not an arbitrary completion threshold — and withholding status information is never acceptable.
Exam objective: PMP ECO Task: Develop an integrated project management plan and plan delivery (Process)
Q8.Midway through a project, market conditions change and the business case no longer supports the project's expected return. What should the project manager do?
Explanation: The business case is owned by the sponsor, and the decision to continue, change, or stop a project whose business case has weakened is a governance decision, not the project manager's alone. The project manager's job is to surface the information promptly and completely so the sponsor can decide with full knowledge. Option C is wrong because an approved charter does not oblige the organization to keep funding a project that no longer makes business sense. Option D is wrong because cancelling a project is a sponsor and governance decision; the project manager does not have that authority. Option A is wrong because quietly changing scope to fix the numbers hides the real issue and breaks the baseline without approval.
Exam objective: PMP ECO Task: Develop an integrated project management plan and plan delivery (Process)