Integrated Planning and Delivery

PMP PMP · Process

By Abu Anns · Last updated 20 November 2026Exam version: July 2026 ECO (current since 9 July 2026)

What integrated planning means

The Process domain opens with one of the largest tasks in the July 2026 ECO: develop an integrated project management plan and plan delivery. "Integrated" is the key word. A project has many moving parts — scope, schedule, cost, quality, resources, communications, risk, procurement, stakeholders — and each has its own plan. The project management plan pulls them all together into one coherent whole, so that a decision in one area is checked against its effects everywhere else. A schedule change that ignores cost, or a scope decision that ignores risk, is not a plan; it is a guess. The exam tests whether you think in this integrated way, and situational questions constantly reward the option that considers the whole project before acting on one part of it.

The project management plan is not a single document written once and filed away. It is a set of subsidiary plans (scope, schedule, cost, quality, resource, communications, risk, procurement, stakeholder engagement) plus three baselines — scope, schedule, and cost — against which performance is measured. It is created during planning, approved by the sponsor and key stakeholders, and then updated through integrated change control whenever an approved change affects it. The exam expects you to know that the plan is a living document: a question describing a project manager who refuses to update the plan after an approved change is describing bad practice.

It starts with the charter

Before there is a plan, there is a project charter — the document that formally authorizes the project and gives the project manager the authority to apply resources to it. The charter is issued by the sponsor, not written by the project manager alone, and it records the project's purpose, measurable objectives, high-level requirements, key stakeholders, major risks, milestones, and budget. The exam tests the charter in two ways. First, the project manager's authority comes from the charter: without it, you have no mandate to spend money or direct resources. Second, the charter is the project's anchor: when scope arguments arise later, the charter (and the business case behind it) is the reference point for what the project is for.

Closely related is the business case, which justifies the project in financial and strategic terms — why this project, why now, what return is expected — and the benefits management plan, which describes how the project's benefits will be measured and realized after delivery. The exam sometimes asks who is responsible for the business case (the sponsor) and when it is revisited (throughout the project, as conditions change — a project whose business case no longer holds should be questioned, not blindly continued).

Baselines: the lines you measure against

A baseline is the approved version of a plan against which performance is compared. The scope baseline is the approved scope statement plus the work breakdown structure (WBS) and the WBS dictionary. The schedule baseline is the approved schedule, with its milestones and critical path. The cost baseline is the approved, time-phased budget — the spending plan over time, which is also the planned value (PV) curve used in earned value management. Together, the three baselines form the performance measurement baseline. The exam expects you to know that baselines change only through formal change control: a project manager who quietly moves a deadline or adds scope without approval is breaking the baseline, not managing the project.

This is also where the exam tests the difference between the cost baseline and the project budget. The budget equals the cost baseline plus the management reserve — money held by the sponsor for unforeseen work that is outside the current scope. The cost baseline itself includes the contingency reserve, money held for known risks that may occur. A question might ask who can authorize spending from the management reserve: the answer is the sponsor (or whoever controls it above the project manager), not the project manager. The contingency reserve, by contrast, is part of the baseline the project manager manages.

Directing and managing the work

Once the plan is approved, the project manager directs and manages the project work: leading the team, applying resources, producing deliverables, and managing the interfaces between the project's parts. This is the executing work, and the exam tests it through scenarios about what to do when reality diverges from the plan. The pattern is always the same: assess the variance, understand its cause and its impact across the whole project, and then choose a response — which may be a corrective action (bringing performance back in line with the plan), a preventive action (stopping a problem before it happens), a defect repair, or a change request. What you do not do is ignore the variance, or fix one part of the project while breaking another.

Work performance data is the raw material for all of this: the actual measurements of what has happened — work completed, costs incurred, defects found, schedule progress. Work performance information is that data analyzed and put into context: earned value figures, variance analysis, forecasts. Work performance reports are the formal documents that communicate the information to stakeholders. The exam sometimes tests the distinction between data, information, and reports, usually with a question about what a status meeting should be based on (information and reports, not raw data).

Planning delivery across predictive, agile, and hybrid approaches

The 2026 ECO is explicit that the exam covers predictive, agile, and hybrid approaches, with roughly 60% of questions reflecting agile, adaptive, or hybrid ways of working. Integrated planning looks different in each. In a predictive project, the plan is detailed up front: the full scope is defined, the schedule is built for the whole project, and changes go through formal control. In an agile project, planning is rolling and adaptive: the team plans in detail for the next iteration and keeps the longer-term plan at a higher level, refining it as learning accumulates. In a hybrid project, the two are combined — for example, a predictive plan for the overall timeline and budget with agile delivery of the software components.

The exam expects you to choose the approach that fits the situation, not to force every project into one method. High uncertainty, changing requirements, and a need for early feedback point toward agile. Stable requirements, regulatory constraints, and fixed scope point toward predictive. A question might describe a project with unclear requirements and a customer who wants to see working product early: the agile-first answer is to use iterative delivery with frequent reviews, not to spend months writing a detailed plan for requirements that will change. Conversely, a question describing a construction project with fixed regulatory requirements points toward predictive planning. The project manager's judgment about the approach is itself part of integrated planning.

Exam mindset for integrated planning

For integrated planning questions, the pattern is: think whole-project, not one-dimensional. Before acting on a variance or a request, assess its impact across scope, schedule, cost, quality, risk, and stakeholders. Use the plan and the baselines as your reference, and change them only through the proper process. Remember that the charter authorizes the project, the sponsor owns the business case and the management reserve, and the project manager owns the integrated plan. And when the situation involves uncertainty or changing requirements, lean toward the adaptive approach — the exam is agile-first, and the plan should fit the project, not the other way around.

Advertisement

Exam traps to watch for

Practice questions

Test yourself on this guide. Answers are checked instantly, with a full explanation for each question.

Q1.A project manager discovers that a deliverable will be two weeks late. Before deciding what to do, what should the project manager do FIRST?

Report an error

Q2.A sponsor asks the project manager to approve spending $50,000 from the management reserve to cover an unexpected regulatory requirement. Who has the authority to approve this spending?

Report an error

Q3.A project manager is assigned to a new project but has not yet received a signed project charter. The sponsor asks the project manager to start hiring team members immediately. What should the project manager do?

Report an error

Q4.A customer asks for a new feature that would add three weeks to the schedule and $40,000 to the cost. The project manager has confirmed the estimates. What should the project manager do NEXT?

Report an error

Q5.A software project has unclear requirements, a customer who wants to see working product early, and a market that changes quickly. Which delivery approach is MOST appropriate?

Report an error

Q6.Which of the following is part of the scope baseline?

Report an error

Q7.A project manager receives work performance data showing that 40% of the work is complete and $120,000 has been spent. To report status to the sponsor, what should the project manager do with this data?

Report an error

Q8.Midway through a project, market conditions change and the business case no longer supports the project's expected return. What should the project manager do?

Report an error