Cost, Finance and Earned Value
PMP PMP · Process
Cost management in one picture
Cost management answers three questions: how much will the project cost (estimate costs), how much are we allowed to spend and when (determine budget), and are we on track (control costs). The July 2026 ECO gives the Process domain one task here: plan and manage finance. The exam tests cost management through concepts and through calculations, and the calculations center on one method: earned value management (EVM). EVM is the most formula-heavy topic on the PMP exam, and it is also one of the most predictable — the same small set of formulas appears in question after question, so learning them properly is one of the highest-return study investments you can make. Our EVM calculator page lets you practise every formula with your own numbers.
Estimating costs uses the same techniques as estimating durations: analogous (based on similar past projects), parametric (based on a statistical rate), bottom-up (detailed estimates rolled up from work packages), and three-point. Costs are estimated for all resources — people, materials, equipment, facilities, and services — and the estimates are rolled up into the cost baseline, the approved time-phased budget. The baseline includes the contingency reserve for known risks but not the management reserve for unforeseen work, which is held outside the baseline by the sponsor. The total project budget is the cost baseline plus the management reserve.
Earned value management: the three core values
EVM compares what you planned to spend, what you have actually earned, and what you have actually spent. It uses three core values, all measured in money:
| Value | Meaning | Also called |
|---|---|---|
| Planned Value (PV) | The budgeted cost of the work scheduled to be done by now | BCWS |
| Earned Value (EV) | The budgeted cost of the work actually completed by now | BCWP |
| Actual Cost (AC) | The real cost incurred for the work done so far | ACWP |
From these three values come the variances and indices that tell you whether the project is on track. Cost variance (CV) = EV - AC: positive means under budget, negative means over budget. Schedule variance (SV) = EV - PV: positive means ahead of schedule, negative means behind. The cost performance index (CPI) = EV / AC: above 1.0 means under budget, below 1.0 means over budget. The schedule performance index (SPI) = EV / PI: above 1.0 means ahead of schedule, below 1.0 means behind. The exam's favorite trap is the direction of the comparison: for cost, you compare EV against AC (what you earned versus what you spent); for schedule, you compare EV against PV (what you earned versus what you planned to earn by now).
A worked example makes this concrete. Suppose PV = $100,000, EV = $80,000, and AC = $90,000. Then CV = 80,000 - 90,000 = -$10,000 (over budget by $10,000), SV = 80,000 - 100,000 = -$20,000 (behind schedule by $20,000 of work), CPI = 80,000 / 90,000 = 0.89 (getting 89 cents of value for every dollar spent), and SPI = 80,000 / 100,000 = 0.80 (progressing at 80% of the planned rate). This project is both over budget and behind schedule — and the exam will often ask you to interpret exactly this kind of combination.
Forecasting: EAC, ETC, VAC, and TCPI
EVM also forecasts where the project will end up. The budget at completion (BAC) is the total budget for the whole project. The estimate at completion (EAC) forecasts the total cost at the end, and there are four standard ways to calculate it, each appropriate in a different situation:
| Situation | EAC formula |
|---|---|
| Future work will be done at the planned rate (the variance was a one-off) | EAC = AC + (BAC - EV) |
| Future work will continue at the current cost performance | EAC = BAC / CPI |
| Future work will be affected by both cost and schedule performance | EAC = AC + [(BAC - EV) / (CPI x SPI)] |
| A new bottom-up estimate is needed (the original estimate is no longer valid) | EAC = AC + bottom-up ETC |
The estimate to complete (ETC) is the forecast cost of the remaining work: ETC = EAC - AC. The variance at completion (VAC) is the forecast overrun or underrun: VAC = BAC - EAC (positive means the project is forecast to finish under budget). The to-complete performance index (TCPI) measures how efficiently the remaining work must be done to hit a target: TCPI = (BAC - EV) / (BAC - AC) to finish on the original budget, or (BAC - EV) / (EAC - AC) to finish on the revised forecast. A TCPI above 1.0 means the team must perform better than planned for the rest of the project — and a TCPI much above 1.1 is usually a sign that the target is unrealistic.
Using the worked example with BAC = $500,000: EAC = BAC / CPI = 500,000 / (80,000/90,000) = $562,500 (assuming current cost performance continues), ETC = 562,500 - 90,000 = $472,500 still to spend, VAC = 500,000 - 562,500 = -$62,500 (forecast to finish $62,500 over budget), and TCPI = (500,000 - 80,000) / (500,000 - 90,000) = 420,000 / 410,000 = 1.02 — the team would need to perform at 102% efficiency to finish on budget, which is demanding but not impossible.
Controlling costs: what the numbers mean for action
The exam does not just ask you to calculate EVM figures; it asks what to do about them. The reasoning chain is the same as everywhere else in the Process domain: understand the cause of the variance before choosing a response. A cost overrun caused by a one-off event (a supplier's price increase that will not recur) calls for a different response than a systematic overrun (the team consistently working slower than estimated). The first case suggests EAC = AC + (BAC - EV), because future work will proceed at the planned rate; the second suggests EAC = BAC / CPI, because current performance will continue. A question that describes the cause of a variance and asks which EAC formula to use is testing exactly this judgment.
Common responses to a cost overrun include reducing scope (through change control), finding cheaper resources, improving efficiency, and re-baselining the budget if the original estimate is no longer valid. What the project manager does not do is hide the overrun, cut quality to save money without approval, or spend from the management reserve without the sponsor. Cost control is also where the exam tests funding: projects are funded in stages, and the project manager must ensure that spending stays within the funding limits for each period, not just within the total budget.
Financial concepts the exam touches
Beyond EVM, the exam tests a small set of financial ideas, mostly in the context of project selection and business value. Return on investment (ROI) measures the return relative to the cost. Net present value (NPV) discounts future cash flows to today's value — a higher NPV is better, and a negative NPV means the project destroys value. Internal rate of return (IRR) is the discount rate at which NPV equals zero — a higher IRR is better. Payback period is how long it takes for the project to recover its investment — shorter is better. Benefit-cost ratio (BCR) divides benefits by costs — above 1.0 means benefits exceed costs. The exam rarely asks for calculations of these (beyond simple cases), but it does ask you to choose between projects using them: given two projects, the one with the higher NPV is usually the better investment, and a project with a BCR below 1.0 should not be selected.
Exam mindset for cost and finance
For cost questions, learn the EVM formulas until they are automatic, and always check the direction of your comparisons: EV minus AC for cost, EV minus PV for schedule, EV divided by AC for CPI, EV divided by PV for SPI. When a question asks for a forecast, read the scenario for the cause of the variance — it tells you which EAC formula to use. And remember that numbers drive decisions: a CPI below 1.0 is not just a number, it is a signal to investigate, to forecast honestly, and to act through the proper process.
Exam traps to watch for
- Mixing up the EVM comparisons: cost compares EV with AC, schedule compares EV with PV. Swapping them gives the wrong variance and the wrong index.
- Using the wrong EAC formula. The scenario's description of the variance cause tells you which one applies: one-off variance means AC + (BAC - EV); continuing performance means BAC / CPI.
- Forgetting that the management reserve is outside the cost baseline. The budget is baseline plus management reserve, and only the sponsor releases the reserve.
- Choosing a project with a lower NPV or a benefit-cost ratio below 1.0. Higher NPV wins; BCR must exceed 1.0 for the project to create value.
Practice questions
Test yourself on this guide. Answers are checked instantly, with a full explanation for each question.
Q1.A project has a planned value (PV) of $100,000, an earned value (EV) of $80,000, and an actual cost (AC) of $90,000. What are the cost variance (CV) and schedule variance (SV)?
Explanation: CV = EV - AC = $80,000 - $90,000 = -$10,000. A negative cost variance means the project is over budget. SV = EV - PV = $80,000 - $100,000 = -$20,000. A negative schedule variance means the project is behind schedule. Option C has both signs wrong — it computes AC - EV and PV - EV instead. Option B swaps the two variances: -$20,000 is the schedule variance, not the cost variance. Option D gets the cost variance right but the schedule variance wrong — EV is less than PV, so the project is behind, not ahead.
Exam objective: PMP ECO Task: Plan and manage finance (Process)
Q2.A project has an earned value (EV) of $80,000 and an actual cost (AC) of $90,000. The budget at completion (BAC) is $500,000. If the project continues at its current cost performance, what is the estimate at completion (EAC)?
Explanation: When future work is expected to continue at the current cost performance, EAC = BAC / CPI. First, CPI = EV / AC = $80,000 / $90,000 = 0.8889. Then EAC = $500,000 / 0.8889 = $562,500. Option D ($510,000) is the result of using EAC = AC + (BAC - EV) = $90,000 + $420,000 = $510,000 — the formula for a one-off variance, which is wrong here because the question says current performance will continue. Option B ($590,000) has no basis in any standard EAC formula. Option A ($500,000) is the BAC, which assumes the project will finish on budget despite running over budget so far.
Exam objective: PMP ECO Task: Plan and manage finance (Process)
Q3.A project is over budget because of a one-time supplier price increase that will not recur. The project manager wants to forecast the total cost at completion. Which EAC formula should be used?
Explanation: When the variance was caused by a one-off event and future work is expected to proceed at the planned rate, the correct formula is EAC = AC + (BAC - EV): the money already spent, plus the remaining work at its originally budgeted cost. Option B (BAC / CPI) is for when current cost performance is expected to continue — wrong here, because the price increase will not recur. Option C is for when both cost and schedule performance will affect future work — not the case here. Option D (a fresh bottom-up estimate) is for when the original estimate is no longer valid at all, which is more drastic than this situation requires.
Exam objective: PMP ECO Task: Plan and manage finance (Process)
Q4.A project has a CPI of 0.85 and an SPI of 1.10. What does this mean?
Explanation: CPI = 0.85 is below 1.0, which means the project is over budget — it is earning only 85 cents of value for every dollar spent. SPI = 1.10 is above 1.0, which means the project is ahead of schedule — it has earned 10% more value than planned by this point. The combination is common: the team is progressing quickly but spending more than planned to do it (for example, by using overtime or premium resources). Option C reverses both readings. Option A reads the CPI as under budget, which is wrong — a CPI below 1.0 always means over budget. Option B reads the SPI as behind schedule, which is wrong — an SPI above 1.0 always means ahead of schedule.
Exam objective: PMP ECO Task: Plan and manage finance (Process)
Q5.A project has a BAC of $200,000, an EV of $120,000, and an AC of $100,000. What is the to-complete performance index (TCPI) to finish on the original budget?
Explanation: TCPI to finish on budget = (BAC - EV) / (BAC - AC) = ($200,000 - $120,000) / ($200,000 - $100,000) = $80,000 / $100,000 = 0.80. A TCPI below 1.0 means the remaining work can be done less efficiently than planned and the project will still finish on budget — which makes sense, since the project is currently under budget (EV exceeds AC). Option D (1.00) would mean the remaining work must be done exactly at planned efficiency. Option C (1.20) has no basis in the TCPI formula. Option A (0.67) has no basis in the TCPI formula.
Exam objective: PMP ECO Task: Plan and manage finance (Process)
Q6.A project manager reports a CPI of 0.75 to the sponsor. The sponsor asks what the project manager will do about it. What is the BEST response?
Explanation: The PMI reasoning chain is: understand the cause before choosing a response. A CPI of 0.75 means the project is significantly over budget, but the right action depends on why — a one-off cost, systematic underestimation, inefficiency, or scope growth each call for a different response. The project manager investigates, forecasts the impact (EAC), and proposes corrective actions through change control. Option D is wrong because cutting scope is a major decision that needs the sponsor's approval and a proper impact assessment, not a unilateral reaction. Option C is wrong because the management reserve is for unforeseen work outside the scope, not for covering cost overruns — and only the sponsor can release it. Option A is wrong because hoping a CPI of 0.75 will fix itself is not management; without action, cost performance typically stays the same or worsens.
Exam objective: PMP ECO Task: Plan and manage finance (Process)
Q7.A project's cost baseline is $400,000 and the management reserve is $50,000. What is the total project budget?
Explanation: The total project budget equals the cost baseline plus the management reserve: $400,000 + $50,000 = $450,000. The cost baseline includes the contingency reserve for known risks; the management reserve sits outside the baseline for unforeseen work. Option A ($400,000) is the cost baseline alone, not the total budget. Option D ($350,000) subtracts the reserve instead of adding it. Option C ($500,000) has no basis in the given figures.
Exam objective: PMP ECO Task: Plan and manage finance (Process)