Business Continuity & Disaster Recovery

CISSP CISSP · Security Operations

By Abu Anns · Last updated 20 November 2026Exam version: April 2024 outline (current until 15 April 2027)

Continuity is a business discipline

Business continuity planning (BCP) and disaster recovery planning (DRP) answer a simple question: when something goes badly wrong, how does the organisation keep operating — and how does it get back to normal? Domain 1 covered the requirements side (the business impact analysis, RTO, RPO, MTD); Domain 7 covers the planning and recovery side. The exam's framing is that continuity is a business responsibility, not an IT project: the business decides what must keep running and how fast it must recover, and IT builds the recovery capability to match. A disaster recovery plan that restores the wrong systems first, or that recovers IT perfectly while the business cannot operate, is a failed plan.

BCP versus DRP

The two plans are related but distinct. The Business Continuity Plan (BCP) is the organisation-wide plan for keeping critical business functions operating during and after a disruption — it covers people, processes, facilities, suppliers and communications, not just technology. The Disaster Recovery Plan (DRP) is the technology-focused subset: how IT systems, data and infrastructure are recovered. The BCP answers "how does the business keep serving customers?"; the DRP answers "how do we get the servers and data back?" The exam tests the scope difference: a plan that covers alternate office space, manual workarounds and supplier communication is a BCP; a plan that covers server restoration and data recovery is a DRP. Both plans need an owner, a maintenance schedule, and regular testing — a plan that has never been tested is a document, not a capability.

Recovery strategies and alternate sites

Recovery sites are classified by how ready they are, and the exam tests the trade-off between cost and recovery speed. A hot site is fully equipped, with hardware, software and current data, ready to take over within hours or minutes — the fastest recovery and the most expensive. A warm site has hardware and connectivity but no current data; data must be restored from backups, so recovery takes longer (typically a day or more) but costs less. A cold site is essentially an empty facility with power, cooling and network — hardware and data must be brought in, so recovery takes days to weeks, but the cost is lowest. Mobile sites are transportable units (trailers with equipment) that can be delivered to a location. Reciprocal agreements — two organisations agreeing to host each other's recovery — are the cheapest option but the least reliable, since both organisations may be affected by the same regional disaster and neither has spare capacity guaranteed. The exam's key insight: the site type must match the RTO. A four-hour RTO cannot be met by a cold site, and a hot site is wasted money for a function with a two-week RTO.

Site typeReadinessTypical recovery timeRelative cost
Hot siteFully equipped with current dataMinutes to hoursHighest
Warm siteHardware ready; data must be restoredHours to a dayMedium
Cold siteEmpty facility with power and coolingDays to weeksLowest
Mobile siteTransportable unit delivered on demandDaysMedium
Reciprocal agreementPartner's facility, if availableUnpredictableLowest (but unreliable)

Backup strategies

Backups are the foundation of data recovery, and the exam tests the backup types and their trade-offs. A full backup copies all selected data; it is the slowest to perform and the largest to store, but the fastest to restore from (a single backup set). An incremental backup copies only data that has changed since the last backup of any type; it is fast and small, but restoration requires the last full backup plus every incremental since — the slowest restore. A differential backup copies all data changed since the last full backup; it grows over time but restoration needs only the full backup plus the latest differential — a middle ground. The 3-2-1 rule is the standard for backup resilience: three copies of the data, on two different media types, with one copy offsite. The exam also covers backup verification (a backup that has never been test-restored is not a backup — it is a hope), backup encryption (backups contain the same sensitive data as production and must be protected equally), and retention (how long backups are kept, driven by the RPO and by legal requirements). Modern approaches include continuous data protection (CDP) and replication (synchronous replication writes to both primary and secondary simultaneously, giving near-zero RPO but requiring low-latency links; asynchronous replication has a small lag but works over longer distances).

Plan development and the BCP process

Developing a continuity plan follows a sequence the exam tests: first, obtain senior management support (without it, the plan has no funding and no authority); second, conduct the business impact analysis to identify critical functions and their recovery requirements; third, develop recovery strategies matched to those requirements; fourth, write the plan — with clear roles (who declares a disaster? who authorises the recovery site? who communicates with staff, customers and regulators?), contact lists, recovery procedures, and manual workarounds; fifth, test the plan; and sixth, maintain the plan through regular review and updates when the business, the technology or the threats change. The exam's most common BCP trap is starting with technology: the correct first step is always management support and the BIA, not buying a hot site or a backup product.

Testing the plan

Plans must be tested, and the exam distinguishes the test types by increasing realism and cost. A checklist review (or desk check) simply verifies the plan document is complete and current. A structured walkthrough has the team talk through the plan step by step. A tabletop exercise presents a scenario and has participants discuss their responses (see the incident response guide). A simulation (or functional exercise) actually performs parts of the recovery, such as failing over a system to the recovery site. A full interruption test (or full-scale exercise) shuts down production and runs the business from the recovery site — the most realistic test and the riskiest, since a failure during the test becomes a real outage. The exam's point: testing should progress from the least disruptive to the most realistic, and every test should produce findings that improve the plan. An untested plan is the most common continuity failure.

Personnel and crisis management

Continuity plans often fail on the human side. The exam covers crisis management — the leadership function during a disruption, typically run by a crisis management team that makes strategic decisions (declaring a disaster, authorising expenditure, communicating externally) while the recovery teams handle the technical work. Emergency response is the immediate priority: life safety comes before everything else, including data and systems. Communication plans must cover internal staff (where to go, what to do), customers (what is affected, when service will return), suppliers, regulators, and the media — with pre-drafted templates and a single spokesperson. Succession planning ensures that if key individuals are unavailable, their deputies can act. And employee safety and support — accounting for all staff, providing assistance — is a responsibility the exam treats as non-negotiable. A plan that recovers the servers but loses track of the people has failed.

Exam mindset for continuity

Continuity questions reward following the process in order: management support, BIA, strategy, plan, test, maintain. Match the recovery strategy to the RTO and RPO — an expensive hot site for a non-critical function is as wrong as a cold site for a four-hour RTO. And remember that testing is not optional: the correct answer to a question about an untested plan is almost always "test it".

Advertisement

Exam traps to watch for

Practice questions

Test yourself on this guide. Answers are checked instantly, with a full explanation for each question.

Q1.An organisation is developing its first business continuity plan. What should be the FIRST step?

Report an error

Q2.A trading system has an RTO of 2 hours and an RPO of 15 minutes. Which recovery strategy BEST meets these requirements?

Report an error

Q3.A backup strategy performs a full backup on Sunday and incremental backups Monday through Saturday. The system fails on Saturday afternoon. How many backup sets are needed to restore the system to its Friday state?

Report an error

Q4.A company’s disaster recovery plan has been written but never tested. The CISO wants to validate the plan with minimal risk to production operations. What is the BEST first test?

Report an error

Q5.During a fire in the office building, the disaster recovery team begins executing the recovery plan. What is the FIRST priority?

Report an error

Q6.An organisation follows the 3-2-1 backup rule. Which configuration satisfies it?

Report an error

Q7.A company’s BCP covers alternate office space, manual workarounds for critical processes, supplier communication, and staff welfare. Its DRP covers server restoration and data recovery. A new manager asks why both plans exist. What is the BEST explanation?

Report an error

Q8.A business impact analysis identifies that the payroll system depends on the HR database, which depends on the identity management system. The recovery plan restores the payroll system first. What is wrong with this plan?

Report an error