EVM Calculator
EVM calculator for the PMP exam: compute CV, SV, CPI, SPI, EAC, ETC, and VAC from PV, EV, AC, and BAC, with a worked example and all formulas explained.
Earned value management (EVM) in one page
Earned value management is the most formula-heavy topic on the PMP exam, and one of the most predictable: the same small set of formulas appears in question after question. Learn them here, then practise with the calculator below using your own numbers.
The three core values
| Value | Meaning |
|---|---|
| Planned Value (PV) | The budgeted cost of the work scheduled to be done by now. |
| Earned Value (EV) | The budgeted cost of the work actually completed by now. |
| Actual Cost (AC) | The real cost incurred for the work done so far. |
Variances and indices
| Measure | Formula | How to read it |
|---|---|---|
| Cost Variance (CV) | EV − AC | Positive = under budget; negative = over budget. |
| Schedule Variance (SV) | EV − PV | Positive = ahead of schedule; negative = behind schedule. |
| Cost Performance Index (CPI) | EV / AC | Above 1.0 = under budget; below 1.0 = over budget. |
| Schedule Performance Index (SPI) | EV / PV | Above 1.0 = ahead of schedule; below 1.0 = behind schedule. |
The exam's favourite trap is the direction of the comparison: for cost, compare EV against AC (what you earned versus what you spent); for schedule, compare EV against PV (what you earned versus what you planned to earn by now).
Forecasting
| Measure | Formula | Meaning |
|---|---|---|
| Estimate at Completion (EAC) | BAC / CPI | Forecast total cost, assuming current cost performance continues. (Other EAC formulas apply when the variance was a one-off, or when both cost and schedule performance will affect future work — see the cost guide.) |
| Estimate to Complete (ETC) | EAC − AC | Forecast cost of the remaining work. |
| Variance at Completion (VAC) | BAC − EAC | Forecast overrun (negative) or underrun (positive). |
| To-Complete Performance Index (TCPI) | (BAC − EV) / (BAC − AC) | Efficiency the remaining work must achieve to finish on budget. Above 1.0 means the team must perform better than planned. |
Worked example
A project has PV = $100,000, EV = $80,000, AC = $90,000, and BAC = $500,000.
- CV = 80,000 − 90,000 = −$10,000 (over budget by $10,000).
- SV = 80,000 − 100,000 = −$20,000 (behind schedule by $20,000 of work).
- CPI = 80,000 / 90,000 = 0.89 (89 cents of value per dollar spent).
- SPI = 80,000 / 100,000 = 0.80 (progressing at 80% of the planned rate).
- EAC = 500,000 / (80,000/90,000) = $562,500 (forecast total cost).
- ETC = 562,500 − 90,000 = $472,500 (still to spend).
- VAC = 500,000 − 562,500 = −$62,500 (forecast to finish $62,500 over budget).
This project is both over budget and behind schedule. Try these numbers in the calculator below to check your understanding, then try your own.
Reading CPI and SPI together
The two indices tell a fuller story together than either does alone. A project with CPI below 1.0 and SPI above 1.0 is progressing quickly but spending too much to do it — often because of overtime or premium resources. A project with CPI above 1.0 and SPI below 1.0 is spending efficiently but moving slowly — perhaps because work is being done carefully, or because the team is understaffed. The worst combination is both indices below 1.0, as in the worked example: over budget and behind schedule at the same time. The exam frequently asks you to interpret a CPI/SPI pair, so practise reading them as a combination rather than as isolated numbers.
Two more exam points are worth locking in. First, the EAC formula depends on the cause of the variance: if the variance was a one-off event that will not recur, use EAC = AC + (BAC − EV), because future work will proceed at the planned rate. If current performance is expected to continue, use EAC = BAC / CPI, as this calculator does. Second, a TCPI much above 1.10 is usually a sign that finishing on budget is unrealistic — the team would have to perform far better than planned for the rest of the project, and the honest response is to re-baseline or to reset expectations with the sponsor rather than to promise the impossible.
EVM calculator
Enter your values and click Calculate. The calculator uses EAC = BAC / CPI (the formula for when current cost performance is expected to continue).