Critical Path Calculator

Critical path calculator for the PMP exam: find the critical path and float in a 6-activity network with editable durations, with a worked example.

By Abu Anns · Last updated 20 November 2026Exam version: July 2026 ECO (current since 9 July 2026)

The critical path method (CPM)

The critical path is the longest sequence of activities through the project network, and it determines the shortest possible project duration. Activities on the critical path have zero float (slack): any delay to them delays the whole project. Activities not on the critical path have float — the amount of time they can be delayed without delaying the project. The exam tests critical path calculations directly, so you must be able to find the longest path through a small network and to compute float.

The network in this calculator

The calculator uses a fixed network of six activities with fixed dependencies. You can change the duration of each activity, and the calculator finds the critical path and the float on each path.

ActivityDepends onDefault duration
A— (start)3 days
BA4 days
CA2 days
DB, C5 days
EC6 days
FD, E (finish)2 days

There are three paths from start to finish:

Worked example

With the default durations (A = 3, B = 4, C = 2, D = 5, E = 6, F = 2):

The critical path is A → B → D → F at 14 days, so the project duration is 14 days. Path 2 has 2 days of float (14 − 12) and Path 3 has 1 day of float (14 − 13). Activity E is on Path 3, so it has 1 day of float: it can be delayed by one day before its path becomes critical.

Try changing the durations to see the critical path move. For example, set A = 5, B = 2, C = 6, D = 3, E = 4, F = 1: Path 1 becomes 11 days, Path 2 becomes 15 days, and Path 3 becomes 16 days — so the critical path switches to A → C → E → F at 16 days. The critical path can change as the project progresses, which is why the project manager must monitor it continuously, not just at the start.

How float is calculated: the forward and backward pass

Behind the calculator's path comparison is the method the exam actually tests: the forward pass and the backward pass through the network. The forward pass computes the early start (ES) and early finish (EF) of each activity, working from the start: an activity's early start is the latest early finish of its predecessors, and its early finish is its early start plus its duration. The backward pass computes the late start (LS) and late finish (LF), working from the end: an activity's late finish is the earliest late start of its successors, and its late start is its late finish minus its duration. Float is then LS − ES (or LF − EF) — the same number either way. Activities with zero float are on the critical path.

In the worked example, activity E has an early start of day 5 (after A finishes on day 3 and C finishes on day 5) and a late start of day 6 (because F must start by day 12 to finish on day 14, and E takes 6 days, so it must start by day 6). Its float is 6 − 5 = 1 day, which matches the path comparison. The exam may ask you to compute float from early and late dates rather than from path lengths, so practise both methods — they always agree.

Key exam points

Critical path calculator

Change any duration and click Calculate. The calculator shows each path length, the critical path, and the float on each path.